深中通道中山大桥超宽钢箱梁悬臂拼装横向变形分析及对策措施
作者:
作者单位:

(广东华路交通科技有限公司 ,广东 广州 510420)

作者简介:

周雨,男,硕士,工程师.E-mail:515422322@qq.com

通讯作者:

中图分类号:

U448.24

基金项目:


Transverse Deformation and Countermeasures of Cantilever Assembly of Super‑Wide Steel Box Girder of Zhongshan Bridge over Shenzhen‑Zhongshan Link
Author:
Affiliation:

(Guangdong Hualu Transportation Technology Co ., Ltd., Guangzhou , Guangdong 510420 , China )

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对斜拉桥超宽幅钢箱悬臂拼装过程中存在横向变形问题,该文根据深中通道中山大桥双向八车道超宽钢箱梁施工特点,分析超宽钢箱梁悬拼安装过程中横向变形产生的主要原因,结合目前国内外宽幅箱梁悬拼施工中匹配高差调整工艺,创新性地提出 “一字梁锁定 +挂索初张拉匹配 ”工艺,较好地解决了中山大桥超宽钢箱梁悬臂拼装横向变形差问题。

    Abstract:

    In view of the transverse deformation of super-wide steel box girders of cable-stayed bridges during the cantilever assembly,the construction characteristics of the two-way eight-lane super-wide steel box girder of Zhongshan Bridge over Shenzhen-Zhongshan Link were analyzed,and the main causes of the transverse deformation during the cantilever assembly of the super-wide steel box girder were investigated.According to the matching height difference adjustment technology in the cantilever assembly construction of the wide box girder in China and abroad,this paper innovatively proposed a matching process of straight beam locking + initial tension of hanging cables,which better solved the problem of poor transverse deformation during the cantilever assembly of the super-wide steel box girder of Zhongshan Bridge.

    参考文献
    相似文献
    引证文献
引用本文

周雨.深中通道中山大桥超宽钢箱梁悬臂拼装横向变形分析及对策措施[J].中外公路,2024,44(4):197-202.
ZHOU Yu. Transverse Deformation and Countermeasures of Cantilever Assembly of Super‑Wide Steel Box Girder of Zhongshan Bridge over Shenzhen‑Zhongshan Link[J]. Journal of China and Foreign Highway,2024,44(4):197-202.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2023-08-23
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2024-07-30
  • 出版日期:
文章二维码
网站二维码
期刊公众号