Abstract:The Sejilashan Tunnel on the G318 Line has many characteristics, such as super-long length, difficult design combining short-term and long-term. It is a rare tunnel project in China that shares the road section of the recent mountain national highway and the far-term expressway. In this paper, based on the characteristics of the project, the key technical problems of overall design, utilization design of parallel heading, ventilation and smoke discharge scheme of near and long-term combination, disaster prevention, evacuation and rescue are studied. The following main findings are concluded: (1) The construction plan is fully integrated with the overall design of the entire process based on the needs of both the near and long term, and the scheme of using a single-tube cross-traffic tunnel for national highways in the near term and a double-tube one-way traffic tunnel for expressways in the long term has significant advantages. (2) The functional positioning and utilization design of the parallel heading for both short-term and long-term stages are particularly critical, its functionality should be fully leveraged., and overall consideration should be taken to maximize the effectiveness of the parallel heading in both the short and long term. This article innovatively proposes a Overall construction plan for the short term, which is to use the main tunnel plus a through parallel heading, and for the long term, which is to use the main tunnel as the right-hand tunnel of the expressway, while expanding the excavation of the parallel heading as the left-hand tunnel of the expressway. (3)In consideration of the characteristics of the Sejilashan Tunnel with high altitude, ultra-long distance, and a through-type parallel heading, it is recommended to adopt full vertical ventilation for the main tunnel in the near term and vertical smoke exhaust through shafts. In the long term, an additional vertical shaft should be added to form a two-zone exhaust ventilation system with exhaust fans in each section. (4)In the near term, the parallel heading is utilized as an evacuation and rescue channel, following the principles of separating people and smoke, rapid escape and rescue, and easy operation and control of ventilation and smoke exhaust, a reasonable and feasible traffic rescue and ventilation and smoke exhaust organization plan should be proposed under fire conditions, additionally, Pathfinder is employed to determine the personnel evacuation time under such fire scenarios.