Ventilation Design and On-Site Effect Testing for Construction of Multiple Working Faces in Tianshan Shengli Tunnel
Author:
Affiliation:

1CCCC Zhongnan Engineering Bureau Co., Ltd., Changsha, Hunan 410116, China;2School of Highway, Chang’an University, Xi’an, Shaanxi 710064, China

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    为探究超长公路隧道多工作面施工中的通风优化与节能问题,该文基于理论计算,分别确定了钻爆法施工和TBM掘进工况下隧道单工作面所需风量;结合隧道施工组织方案提出两种通风方案,根据轴流风机的配置功率对两种通风方案进行比选;在推荐方案基础上,设计了排污射流风机的布置方案,最终通过现场污染物浓度实测验证其可行性。研究表明:钻爆法施工与TBM法掘进的工作面所需风量分别为1 980 m3/min和1 500 m3/min,均由其洞内最小允许风速控制;多工作面交替施工方案风机总功率仅为常规施工方案的39%,显著降低了能耗;现场实测表明,多工作面交替施工方案可满足施工期风速与氧气含量要求,CO、SO2、PM2.5、PM10的平均质量浓度均低于《公路隧道施工技术规范》(JTG/T 3660—2020)容许值,表明方案切实可行。但是在开挖爆破期间局部区域短时污染物聚集,需适当提高供风量。研究成果有效指导了天山胜利隧道施工通风,并可为类似工程提供参考。

    Abstract:

    To explore the ventilation optimization and energy saving issues in the construction of multiple working faces in extra-long highway tunnels, the air volumes required for a single working face under drilling and blasting construction conditions and TBM tunneling conditions were determined respectively based on theoretical calculations. Combined with the tunnel construction organization scheme, two ventilation schemes were proposed, and they were compared and selected according to the configured power of axial fans. Based on the recommended scheme, the layout scheme of pollutant-discharging jet fans was designed, and its feasibility was finally verified by on-site measurements of pollutant concentrations. The research shows that the air volumes required for the working faces of the drilling and blasting method and the TBM method are 1 980 m3/min and 1 500 m3/min, respectively, which are both controlled by the minimum allowable air velocity in the tunnel. The total fan power of the alternating construction scheme for multiple working faces is only 39% of that of the conventional construction scheme, which significantly reduces energy consumption. On-site measurements indicate that the alternating construction scheme for multiple working faces can meet the requirements of air velocity and oxygen content during the construction period. The average mass concentrations of CO, SO2, PM2.5, and PM10 are lower than the allowable values specified in the Technical Specifications for Construction of Highway Tunnel (JTG/T 3660—2020), indicating that the scheme is highly feasible. However, short-term pollutant accumulation occurs in local areas during excavation blasting, requiring an appropriate increase in air supply. The research results effectively guide the construction ventilation of Tianshan Shengli Tunnel and can provide a reference for similar projects.

    参考文献
    相似文献
    引证文献
引用本文

熊子壹,贾海洋,索飞宇,等.天山胜利隧道多工作面施工通风设计及效果现场测试[J].中外公路,2026,46(3):216-226.
XIONG Ziyi, JIA Haiyang, SUO Feiyu, et al. Ventilation Design and On-Site Effect Testing for Construction of Multiple Working Faces in Tianshan Shengli Tunnel[J]. Journal of China & Foreign Highway,2026,46(3):216-226.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2024-08-27
  • 最后修改日期:2025-11-17
  • 录用日期:
  • 在线发布日期: 2026-06-27
  • 出版日期:
文章二维码
网站二维码
期刊公众号